Planned Federal FY: |
2026 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
NORWOOD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Adj. TFPC: $28,699,272 (CMAQ, HSIP, NHPP, STBG). Project ACd 2026 - 2027.
|
|
Category |
FA - Hwy Safety Improvement Prgm (HSIP) |
|
Federal Cost: |
$568,551.60 |
State Cost: |
$63,172.40 |
Total Cost: |
$631,724.00 |
|
|
|
Planned Federal FY: |
2026 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
NORWOOD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Adj. TFPC: $28,699,272 (CMAQ, HSIP, NHPP, STBG). Project ACd 2026 - 2027.
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS |
|
Federal Cost: |
$3,999,120.80 |
State Cost: |
$999,780.20 |
Total Cost: |
$4,998,901.00 |
|
|
|
Planned Federal FY: |
2026 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
NORWOOD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Adj. TFPC: $28,699,272 (CMAQ, HSIP, NHPP, STBG). Project ACd 2026 - 2027.
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$4,396,197.60 |
State Cost: |
$1,099,049.40 |
Total Cost: |
$5,495,247.00 |
|
|
|
Planned Federal FY: |
2027 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
NORWOOD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Adj. TFPC: $28,699,272 (CMAQ, HSIP, NHPP, STBG). Project ACd 2026 - 2027.
|
|
Category |
FA - Congestion Mitigation/Air Quality (CMAQ) |
|
Federal Cost: |
$2,400,000.00 |
State Cost: |
$600,000.00 |
Total Cost: |
$3,000,000.00 |
|
|
|
Planned Federal FY: |
2027 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
NORWOOD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Adj. TFPC: $28,699,272 (CMAQ, HSIP, NHPP, STBG). Project ACd 2026 - 2027.
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS |
|
Federal Cost: |
$2,858,720.00 |
State Cost: |
$714,680.00 |
Total Cost: |
$3,573,400.00 |
|
|
|
Planned Federal FY: |
2027 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
NORWOOD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Adj. TFPC: $28,699,272 (CMAQ, HSIP, NHPP, STBG). Project ACd 2026 - 2027.
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$8,800,000.00 |
State Cost: |
$2,200,000.00 |
Total Cost: |
$11,000,000.00 |
|
|
|
|