Project Description:
LEXINGTON- SAFE ROUTES TO SCHOOL (BOWMAN SCHOOL)
The project will install sidewalks, ADA-compliant ramps, crosswalks and pedestrian signage on Philip Road, Lantern Lane, Dawes Road, Buckman Drive, and the western most part of Locust Avenue. ADA-compliant ramps, crosswalks and signage will also be installed at the intersection of Worthen Road East at Pleasant Street and Philip Road.
Location:
  • Town of Lexington
  • Resident Engineer: James Herrick
    Construction Contract Value: $342,959.92
    Construction Bid Price: $269,059.81
    Initial Construction Estimate: $298,855.00
    District: District 4

    Contracts (1) Progress
    # 66935 -- Construction Contract
    Sidewalk Construction along Phillip and Dawes Roads, Buckman Drive, Lantern Lane and Locust Avenue (Safe Routes to School) – Bowman School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/10/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/14/2009
    Project Initiation Form PIF Entered 10/14/2009
    Project Initiation Form PRC Submitted 10/16/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 08/28/2010
    Project Management
    100% Design 100% Package Received 06/29/2010
    100% Design 100% Package Comments to DE 08/09/2010
    25% Design 25% Package Received 01/27/2010
    25% Design 25% Package Comments to DE 05/07/2010
    25% Design Design Public Hearing 05/24/2010
    75% Design 75% Package Received 01/27/2010
    75% Design 75% Package Comments to DE 05/07/2010
    Final Design PS&E Received 08/18/2010
    Final Design PS&E to FAPRO 08/25/2010