SWAMPSCOTT- SAFE ROUTES TO SCHOOL (STANLEY SCHOOL)
The project will reduce the crossing distance for pedestrians at the intersection of Humphrey Street and Salem Street by introducing a pedestrian refuge median. New crosswalks and signs will also be included. The pedestrian crossing distances on Orchard Road will be reduced by installing curb bump-outs at crosswalks and reducing the curb radii at intersecting streets. Orchard Road will be restriped to better define the parking lane and travel lane. New ADA-compliant ramps and school zone crossing signs will be also be added.
Location:
  • Town of Swampscott
  • Resident Engineer: Erik Berzins
    Construction Contract Value: $279,396.00
    Construction Bid Price: $248,451.75
    Initial Construction Estimate: $251,481.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75498 -- Construction Contract
    Sidewalk and Pedestrian Safety Improvements on Sections of Orchard Circle, Orchard Road & Whitman Road (Safe Routes to School - Stanley School) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/16/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/15/2009
    Project Initiation Form PIF Entered 10/15/2009
    Project Initiation Form PRC Submitted 10/16/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/08/2012
    Project Management
    100% Design 100% Package Received 05/07/2012
    25% Design 25% Package Received 11/02/2011
    25% Design Design Public Hearing 04/03/2012
    75% Design 75% Package Received 11/02/2011
    75% Design 75% Package Comments to DE 02/01/2012
    Final Design PS&E Received 07/17/2012