Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STONEHAM- SAFE ROUTES TO SCHOOL (CENTRAL SCHOOL)
The existing sidewalk on Central Street will be reconstructed. The school entrance will be improved by adding new crosswalk signs and pavement markings to control traffic flow and provide a fire lane. A new sidewalk will be installed along the school exit driveway. The school exit drive will be reconstructed to provide a multi-use path and vehicle egress.
Location:
  • Town of Stoneham
  • Resident Engineer: Michael Bartolo
    Construction Contract Value: $359,050.25
    Construction Bid Price: $322,246.05
    Initial Construction Estimate: $382,575.00
    District: District 4

    Contracts (1) Progress
    # 67219 -- Construction Contract
    Sidewalk Construction and Related Work on a Section of Central Street (Safe Routes to School – Central School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/31/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/15/2009
    Project Initiation Form PIF Entered 10/15/2009
    Project Initiation Form PRC Submitted 10/19/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/11/2010
    Project Management
    25% Design Design Public Hearing 06/10/2010
    75% Design 75% Package Received 03/01/2010
    75% Design 75% Package Comments to DE 04/15/2010
    Final Design PS&E Received 07/14/2010
    Final Design PS&E Received 08/27/2010
    Final Design PS&E to FAPRO 09/03/2010