Project Description:
DEDHAM- BRIDGE REPLACEMENT, D-05-003 (33K), NEEDHAM STREET OVER GREAT DITCH
It is anticipated that the structure will be replaced with a single span superstructure of approximately 84 feet. The additional required superstructure depth shall be accommodated by raising the profile as little as possible. The proposed bottom chord elevation should not be reduced. The abutments are to be located behind the existing abutments. They will be integral with the superstructure and supported on piles. The existing abutments shall be left in place to be part of the scour protection system and, if necessary, the construction dewatering system. They shall be cut down to facilitate inspection access to the new abutments and beam ends. These parameters shall be verified with the Geotechnical Report, the Hydraulic Report, the Survey, and the consultant’s own investigations. The bridge profile is expected to remain approximately the same. The minimum under clearance of the bridge cannot be reduced. This profile shall be verified with the proposed superstructure depth and the Hydraulic Report. The curb-to-curb width of the bridge shall be 32 feet. There shall be a new 5.5 foot sidewalk. The bridge rail shall be type S3-TL4. Highway guardrail transitions shall be located on independent bases. Adequate lighting shall be provided on the approach roadway curve (restore any existing lighting and add additional as necessary.) The scour protection of the abutments is required and shall be included on the consultant’s drawings and special provisions. Work in the water shall be eliminated or reduced to the extent possible.
Location:
  • Town of Dedham
  • Resident Engineer: Edward Moschella Jr
    Construction Contract Value: $3,116,819.93
    Construction Bid Price: $2,819,836.30
    Initial Construction Estimate: $2,821,000.00
    District: District 6

    Contracts (5) Progress
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 64305 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86121 -- Construction Contract
    Bridge Replacement Br. No. D-05-003 (Precast Concrete NEBT Beams) Needham Street over Great Ditch. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/19/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2009
    Project Initiation Form PIF Entered 04/06/2011
    Project Initiation Form PRC Submitted 04/07/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 12/20/2014
    Project Management
    100% Design 100% Package Received 10/14/2014
    100% Design 100% Package Comments to DE 11/14/2014
    25% Design 25% Package Received 11/29/2012
    25% Design 25% Package Comments to DE 01/09/2013
    25% Design 25% Package Approved 05/15/2013
    25% Design Design Public Hearing 09/25/2013
    25% Design 25% Plans Complete 08/30/2013
    75% Design 75% Package Received 05/30/2014
    75% Design 75% Package Comments to DE 07/22/2014
    Final Design PS&E Received 12/08/2014
    Final Design PS&E to FAPRO 12/17/2014
    Consultant Contract Process NTP Issued 05/06/2011