Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LONGMEADOW- RESURFACING & RELATED WORK ON ROUTE 5 (LONGMEADOW STREET), FROM EDGEWOOD STREET TO WARREN TERRACE, INCLUDES CULVERT REPAIRS AT COOLEY BROOK
Project includes resurfacing and roadway drainage system improvements from Edgewood Street northerly to Warren Terrace. Work will also include lining of the existing 4'x4' box culvert at Cooley Brook along with new headwalls and slope repairs at both culvert ends.
Location:
  • Town of Longmeadow
  • Resident Engineer: James Hurley
    Construction Contract Value: $935,977.00
    Construction Bid Price: $835,336.80
    Initial Construction Estimate: $664,508.50
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 80857 -- Construction Contract
    Drainage Rehabilitation (Including Slip Lining and Cured-in-Place Pipe) and Related Work on a Section of Route 5 (Longmeadow Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/11/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/20/2009
    Project Initiation Form PIF Entered 10/26/2009
    Project Initiation Form PRC Submitted 10/26/2009
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 12/28/2013
    Project Management
    100% Design 100% Package Received 04/10/2013
    100% Design 100% Package Comments to DE 05/10/2013
    25% Design 25% Package Received 08/18/2011
    25% Design 25% Package Comments to DE 10/06/2011
    25% Design Design Public Hearing 08/22/2012
    75% Design 75% Package Received 11/15/2012
    75% Design 75% Package Comments to DE 01/09/2013
    Final Design PS&E Received 09/06/2013
    Final Design PS&E to FAPRO 11/13/2013