Project Description:
TAUNTON- INTERCHANGE IMPROVEMENTS AT ROUTES 24 & 140, INCLUDING REPLACING T-01-045 AND T-01-046
Work on this project consists of interchange improvements at Routes 24 and 140, including replacement of the Route 24 bridge over Route 140. The ramp system will be modified to improve vehicular flow to and from each limited access highway.
Location:
  • City of Taunton
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Amy Aveiro
    Construction Bid Price: $116,498,483.53
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: Completed the deck portion of demolition on bridge T-01-046 and south abutment backwall. Completed the southernly section of the Cotley Rivers water diversion sheeting. Continued median excavation to Station 245+00 on Route 24 for future slotted drain installation. Began water diversion installation on the north side of the Cotley River. Removal of girder number 8 from median demo on 9/19/21 and begin framing the backwall on South abutment. Begin work for Wall 5 footing by Ramp F on 9/27/21 - 10/8/21. Normal work hours are Monday thru Friday 7:00 AM to 3:30PM. Scheduled work hours are Sunday through Friday, 8:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. Roadway closed to traffic. Detour in place. (as of 09/16/2021)

    Contracts (10) Progress
    # 112402 -- Construction Contract
    Bridge Replacements and Related Work (Including Signals & Wall Structures) along a Section of Route 24 at Interchange 12, Br. No. T-01-046 (Steel) over Route 140 and Br. Nos. 8% Complete
    # 56818 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as need, assignment basis over a period of 60 months. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80660 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 02/17/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    Planned Federal FY: 2021
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: TAUNTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Project AC'd over 2020-2022; TFPC: $126,517,047; HIP (SW): $24,328,985; HIP (BOS-Flex): $17,975,820; HIP BR (2020): $14,994,841; REP funding: $28,243,278; Total cost: $154,760,325
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $11,995,872.80
    State Cost: $2,998,968.20
    Total Cost: $14,994,841.00

    Planned Federal FY: 2021
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: TAUNTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Project AC'd over 2020-2022; TFPC: $126,517,047; HIP (SW): $24,328,985; HIP (BOS-Flex): $17,975,820; HIP BR (2020): $14,994,841; REP funding: $28,243,278; Total cost: $154,760,325
  • Category FA - Hwy Infrast. Prgm (HIP) - Non-Interstate
    Federal Cost: $33,843,844.00
    State Cost: $8,460,961.00
    Total Cost: $42,304,805.00

    Planned Federal FY: 2022
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: TAUNTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Project AC'd over 2020-2022; TFPC: $126,517,047; HIP (SW): $24,328,985; HIP (BOS-Flex): $17,975,820; HIP BR (2020): $14,994,841; REP funding: $28,243,278; Total cost: $154,760,325
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $21,064,223.20
    State Cost: $5,266,055.80
    Total Cost: $26,330,279.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/20/2009
    Project Initiation Form PIF Entered 10/21/2009
    Project Initiation Form PRC Submitted 10/20/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 08/08/2020
    Project Management
    100% Design 100% Package Received 04/06/2020
    25% Design 25% Package Received 12/04/2018
    75% Design 75% Package Received 06/17/2019
    75% Design 75% Package Comments to DE 07/19/2019
    Final Design PS&E Received 07/13/2020
    Final Design PS&E to FAPRO 07/13/2020
    Final Design PS&E Received - Resub 1 08/28/2020