EASTHAMPTON- HOLYOKE- RESURFACING & RELATED WORK ON ROUTE 5, MM 16.014 IN HOLYOKE TO MM 20.427 IN EASTHAMPTON (4.43 MILES)
The purpose of this project is to resurface Route 5 in Easthampton and Holyoke. Work will consist of micromilling 2” from the existing paved surface and repaving with a 2” HMA surface course modified top with Latex modified binder. Work will also include repairing or replacing signs, guardrail ends, curb/edging, sidewalks and ramps as needed, sight distance clearing and new pavement markings. The project limits are as follows: Route 5 from MM 16.0 (beginning of state highway) to MM 20.5 (Oxbow bridge), for a project length of 4.5 miles.
Location:
  • Town of Easthampton
  • City of Holyoke
  • Resident Engineer: Richard Wonderlie
    Construction Contract Value: $2,447,345.00
    Construction Bid Price: $2,170,550.75
    Initial Construction Estimate: $2,076,662.00
    District: District 2

    Contracts (1) Progress
    # 80253 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 5 (Mount Tom Road and Northampton Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/16/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/23/2009
    Project Initiation Form PIF Entered 10/23/2009
    Project Initiation Form PRC Submitted 10/23/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 10/19/2013
    Project Management
    75% Design 75% Package Received 11/19/2009
    75% Design 75% Package Comments to DE 11/25/2009
    Final Design PS&E Received 12/17/2009
    Final Design PS&E Received 05/12/2010
    Final Design PS&E Received 09/08/2010
    Final Design PS&E Received 10/07/2013
    Final Design PS&E to FAPRO 10/09/2013