BELLINGHAM- BRIDGE DEMOLITION, B-06-011, ROUTE 126 OVER CSX RAILROAD (ABANDONED) & INSTALLATION OF BIKE PATH CULVERT
The work included in this project includes the demolition of Bridge No B-06-011. The bridge will be replaced with a culvert to accomodate any future bike paths along the abandoned railway bed.
Location:
  • Town of Bellingham
  • Resident Engineer: Scott Fitzgerald
    Construction Contract Value: $2,760,309.48
    Construction Bid Price: $2,567,481.80
    Initial Construction Estimate: $2,624,895.00
    District: District 3

    Contracts (3) Progress
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 84999 -- Construction Contract
    Bridge Replacement Br. No. B-06-011 (Concrete Arch) Route 126 (North Main Street) over a Proposed Rail Trail Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/28/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/23/2009
    Project Initiation Form PIF Entered 10/23/2009
    Project Initiation Form PRC Submitted 10/26/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/20/2014
    Project Management
    25% Design 25% Package Received 05/08/2013
    25% Design 25% Package Comments to DE 05/31/2013
    25% Design 25% Package Comments to DE 11/07/2013
    25% Design 25% Package Comments to DE 02/07/2014
    25% Design Design Public Hearing 02/11/2014
    75% Design 75% Package Received 05/30/2014
    75% Design 75% Package Comments to DE 08/05/2014
    75% Design 75% Plans Approved 08/12/2014
    75% Design 75% Plans Complete 08/12/2014
    Final Design PS&E Received 09/10/2014
    Final Design PS&E Received 02/24/2015
    Final Design PS&E Received 03/13/2015
    Final Design PS&E to FAPRO 09/16/2014