Project Description:
DISTRICT 5- CATCH BASIN CLEANING AT VARIOUS LOCATIONS IN AREA 5D
Work on this project consists of catch basin cleaning on Cape Cod and Wareham.
Location:
Resident Engineer: Dilip Patel
Construction Contract Value: $272,179.30
Construction Bid Price: $201,509.30
Initial Construction Estimate: $240,325.00
District: District 5

Contracts (1) Progress
# 68185 -- Construction Contract
DISTRICT 5 - Scheduled and Emergency Catch Basin Cleaning at Various Locations in Area 5D 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/24/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/26/2009
    Project Initiation Form PIF Entered 10/27/2009
    Project Initiation Form PRC Submitted 10/27/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 07/03/2010
    Project Status Advertised 02/19/2011
    Project Management
    Final Design PS&E Received 12/11/2009
    Final Design PS&E to FAPRO 02/04/2010
    Final Design PS&E to FAPRO 10/26/2010