BOSTON- PAVEMENT, BARRIER, LIGHTING, & MISCELLANEOUS ELECTRICAL UPGRADES ON I-90 PRUDENTIAL TUNNEL & APPROACHES
|
| Location: |
|
| Resident Engineer: | Charles Labbee![]() |
| Construction Contract Value: | $14,843,859.00 |
| Construction Bid Price: | $9,755,530.00 |
| Initial Construction Estimate: | $11,935,947.00 |
| District: | District 6 |
|