| Project Description: |
CHESTER- RETAINING WALL REPLACEMENT ALONG ROUTE 20
This project will replace an existing, failed, dry-laid stone retaining wall with a cast-in-place reinforced concrete retaining wall. The wall supports the highway (fill section), and is not visible from the roadway. The failed wall is approximately 30 ft long and 7 ft high, and lies between two sections of reinforced concrete retaining wall; the proposed wall will connect these two existing wall sections.
|
| Location: |
|
| Resident Engineer: | Richard Miskinis Jr![]() |
| Construction Contract Value: | $223,008.48 |
| Construction Bid Price: | $189,834.00 |
| Initial Construction Estimate: | $162,184.00 |
| District: | District 1 |
|