| Project Description: |
BOSTON- HVAC UPGRADES & RELATED WORK WITHIN DISTRICT HQ BUILDING AT 185 KNEELAND
The purpose of this project is to replace the air conditioning units at the former Central Artery/Tunnel project administration building located at 185 Kneeland Street in Boston.
|
| Location: |
|
| Resident Engineer: | Charles Labbee![]() |
| Construction Contract Value: | $5,640,592.00 |
| Construction Bid Price: | $4,904,950.00 |
| Initial Construction Estimate: | $5,944,260.00 |
| District: | District 6 |
|
Bridges |
||||||||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||