Project Description:
BOSTON- HVAC UPGRADES & RELATED WORK WITHIN DISTRICT HQ BUILDING AT 185 KNEELAND
The purpose of this project is to replace the air conditioning units at the former Central Artery/Tunnel project administration building located at 185 Kneeland Street in Boston.
Location:
  • City of Boston
  • Resident Engineer: Charles Labbee
    Construction Contract Value: $5,640,592.00
    Construction Bid Price: $4,904,950.00
    Initial Construction Estimate: $5,944,260.00
    District: District 6

    Contracts (2) Progress
    # 63791 -- Construction Contract
    HVAC Upgrades and Related Work at District 6 Headquarters - 185 Kneeland Street. (MTA) Completed
    # 64305 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/06/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/27/2009
    Project Initiation Form PIF Entered 10/27/2009
    Project Initiation Form PRC Submitted 10/27/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Status Advertised 04/03/2010
    Project Management
    Final Design PS&E Received 03/29/2010
    Final Design PS&E to FAPRO 03/31/2010