Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- CALLAHAN TUNNEL REHABILITATION INCLUDING CURB, ROADWAY & WALL PANELS
The purpose of this project is to rehabilitate the the Callahan Tunnel curb, roadway and wall panels in the City of Boston.
Location:
  • City of Boston
  • Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $25,210,633.00
    Construction Bid Price: $19,307,507.50
    Initial Construction Estimate: $26,506,274.00
    District: District 6

    Contracts (7) Progress
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55545 -- Design -- Bridge Open End
    Work will consist of reviewing Bridge Project estimates and preparing guidance for estimating of Bridge projects. Final
    # 64305 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 69764 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 78184 -- Construction Contract
    Callahan Tunnel Rehabilitation Including Curb, Roadway and Wall Panels. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/28/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/27/2009
    Project Initiation Form PIF Entered 10/27/2009
    Project Initiation Form PRC Submitted 10/27/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Review Committee Letter 12/04/2009
    Project Status Advertised 06/29/2013
    Project Management
    100% Design 100% Package Received 10/31/2012
    100% Design 100% Package Comments to DE 01/04/2013
    75% Design 75% Package Received 10/31/2012
    Final Design PS&E Received 05/02/2013
    Final Design PS&E to FAPRO 06/25/2013