Project Description:
LAKEVILLE- FREETOWN- NEW BEDFORD- FAIRHAVEN- MEDIAN CABLE BARRIER INSTALLATION ON ROUTE 140 & ROUTE I-195
Work on this project consists of cable guardrail installation in the median on Route 140 in New Bedford and Route I-195 in Fairhaven.
Location:
  • Town of Fairhaven
  • Town of Freetown
  • Town of Lakeville
  • City of New Bedford
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Luciano Rabito
    Estimated Total Contract Cost: $1,392,610.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information