Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 1- DISTRICT 2- DISTRICT 3- DISTRICT 6- FIBER ENHANCEMENT ON I-90 (ITS)
This project will add equipment at existing facilities to create a shared Wide Area Network (WAN) to transport voice, video and data for all transportation agencies. The technology employed will be expandable to share up to 40 separate 10 GPS networks over 4 fibers.
Location:
Resident Engineer: Brian Kelleher
Construction Contract Value: $2,903,473.00
Construction Bid Price: $1,317,872.62
Initial Construction Estimate: $1,436,705.00

Contracts (1) Progress
# 66842 -- Construction Contract
DWDM Equipment Installation for Intelligent Transportation System (ITS) Enhancement along Interstate 90 (ARRA Project) (Readvertised) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/18/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/28/2009
    Project Initiation Form PIF Entered 10/28/2009
    Project Initiation Form PRC Submitted 10/28/2009
    Project Status Advertised 01/30/2010
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 01/12/2010
    75% Design 75% Package Received 12/04/2009
    Final Design PS&E Received 09/02/2010
    Final Design PS&E to FAPRO 01/22/2010