Project Description:
BOSTON- FURNISHING & INSTALLATION OF INTERCHANGE LIGHTING AT 3 LOCATIONS: I-90, I-93 & ROUTE 1A (CRC 20)
CRC 20 - Furnish & Install Interchange Lighting at 3 Locations: I-90, I-93, & Rte. 1A
Location:
  • City of Boston
  • Construction Begins: Winter 2009/2010
    Resident Engineer: James O'Leary
    Construction Contract Value: $4,034,986.00
    Construction Bid Price: $3,787,986.00
    Initial Construction Estimate: $7,660,986.50
    District: District 6

    Contracts (1) Progress
    # 61503 -- Construction Contract
    I-93 Lighting North of Central Atery/Tunnel and I-90/ Route 1A Interchange Electrical. (CRC 20) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/13/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/29/2009
    Project Initiation Form PIF Entered 10/29/2009
    Project Initiation Form PRC Submitted 10/29/2009
    Project Status Advertised 10/31/2009
    Project Management
    100% Design 100% Package Received 10/20/2009
    Final Design PS&E Received 10/26/2009
    Final Design PS&E to FAPRO 10/28/2009