Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- TRENCH DRAIN REPLACEMENTS & ISOLATION JOINT REPAIRS @ TUNNEL PORTALS (CRC 5)
Location:
  • City of Boston
  • Resident Engineer: John Wagner
    Construction Contract Value: $4,335,480.00
    Construction Bid Price: $4,235,480.00
    Initial Construction Estimate: $4,748,300.00
    District: District 6

    Contracts (1) Progress
    # 68161 -- Construction Contract
    Trench Drain Replacement and Isolation Joint Leak Sealing at Central Artery Tunnel (I-93/I-90) Portals Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/17/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/29/2009
    Project Initiation Form PIF Entered 10/29/2009
    Project Initiation Form PRC Submitted 10/29/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Review Committee Letter 12/04/2009
    Project Status Advertised 01/01/2011
    Project Management
    Final Design PS&E Received 12/21/2010
    Final Design PS&E to FAPRO 12/21/2010