Project Description: |
BOSTON- TUNNEL REMEDIATION & SUBSURFACE EXPLORATION (CRC 4 - PHASE I)
|
Location: |
|
Resident Engineer: | John Wagner |
Construction Contract Value: | $8,760,785.00 |
Construction Bid Price: | $5,876,770.00 |
Initial Construction Estimate: | $7,494,520.00 |
District: | District 6 |
|
Bridges |
|
|
|
|