Project Description:
BOSTON- RESURFACING & RELATED WORK AT VARIOUS LOCATIONS (AREA 3)
Work will consist of resurfacing and related work at various locations in the city of Boston (locations TBD).
Location:
  • City of Boston
  • Resident Engineer: Scott Leisey
    Construction Contract Value: $3,506,764.00
    Construction Bid Price: $3,064,937.71
    Initial Construction Estimate: $3,654,804.00
    District: District 4

    Contracts (1) Progress
    # 62019 -- Construction Contract
    Resurfacing and Related Work on Sections of 9 Streets (Area 3). (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/04/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/06/2009
    Project Initiation Form PIF Entered 11/06/2009
    Project Initiation Form PRC Submitted 11/06/2009
    Project Status Advertised 12/19/2009
    Project Management
    100% Design 100% Package Received 11/23/2009
    100% Design 100% Package Comments to DE 12/03/2009
    100% Design 100% Plans Complete 12/07/2009
    Final Design PS&E Received 12/07/2009
    Final Design PS&E to FAPRO 12/09/2009