Project Description:
WILLIAMSTOWN- BRIDGE REPLACEMENT, W-37-009, HOPPER ROAD OVER GREEN RIVER
This structure shall be widened with two 11 foot lanes and two 5 foot shoulders. No sidewalk shall be provided per Town's request.
Location:
  • Town of Williamstown
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $2,805,438.00
    Construction Bid Price: $2,547,055.00
    Initial Construction Estimate: $2,827,295.02
    District: District 1

    Contracts (5) Progress
    # 54620 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection, and design and analysis of complex foundation rehabilitation projects. Final
    # 58594 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 84366 -- Construction Contract
    Bridge Replacement (Steel) (W-37-009) -Hopper Road over the Green River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/13/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/12/2009
    Project Initiation Form PIF Entered 02/28/2012
    Project Initiation Form PRC Submitted 02/28/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 08/16/2014
    Project Management
    100% Design 100% Package Received 03/24/2014
    100% Design 100% Package Comments to DE 05/20/2014
    100% Design 100% Plans Approved 05/09/2014
    100% Design 100% Plans Approved 08/06/2014
    100% Design 100% Plans Complete 03/28/2014
    25% Design 25% Package Received 05/14/2013
    25% Design 25% Package Comments to DE 05/23/2013
    25% Design Design Public Hearing 09/24/2013
    25% Design 25% Plans Complete 11/25/2013
    75% Design 75% Package Received 01/10/2014
    75% Design 75% Package Comments to DE 03/24/2014
    Final Design PS&E Received 06/24/2014
    Final Design PS&E Received 08/06/2014
    Final Design PS&E to FAPRO 08/13/2014
    Consultant Contract Process Scope to DE 05/22/2012
    Consultant Contract Process NTP Issued 08/21/2012