QUINCY- BRIDGE REHABILITATION, Q-01-009, HANCOCK STREET OVER SAGAMORE STREET (PHASE II)
The purpose of this project is to replace the superstructure of the Hancock Street Bridge over Sagamore Street, the MBTA Red Lines and the MBTA Commuter Rail in the City of Ouincy. The work includes the complete superstructure replacement in Spans 1-3 and the rehabilitation of Span 4 where the existing beams are to remain. The new butted prestressed concrete beams in Spans 1 to 3 and the existing butted prestressed concrete beams in Span 4 will be overlain by a new 6" concrete deck slab and a hot mix asphalt (superpave) overlay. The structure shall remain open to one lane of traffic in each direction at all times during construction. Also included is the minor work on the roadway approaches to the limits shown on the Plans which includes, but is not limited to, minor roadway profile adjustments, excavation and removal of the existing pavement, placement of a new pavement structure, the installation of a water main, new highway guardrail transitions, the reconstruction of sections of sidewalk, the construction of new wheelchair ramps and the installation of new pavement markings and signs.
Location:
  • City of Quincy
  • Resident Engineer: John Chan
    Construction Contract Value: $4,583,967.31
    Construction Bid Price: $3,440,519.25
    Initial Construction Estimate: $4,709,551.00
    District: District 6

    Contracts (2) Progress
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 63978 -- Construction Contract
    Bridge Rehabilitation (Q-01-009) (Concrete) – Hancock Street over Sagamore Street and the MBTA Railroad. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/30/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/16/2009
    Project Initiation Form PIF Entered 11/25/2009
    Project Status Advertised 04/17/2010
    Project Status Advertised 05/15/2010
    Project Management
    100% Design 100% Package Received 01/07/2010
    100% Design 100% Package Received 03/15/2010
    100% Design 100% Package Comments to DE 01/27/2010
    100% Design 100% Package Comments to DE 03/15/2010
    100% Design 100% Plans Complete 04/13/2010
    75% Design 75% Package Received 01/07/2010
    Final Design PS&E Received 02/23/2010
    Final Design PS&E to FAPRO 04/14/2010
    Consultant Contract Process Scope to DE 08/31/2009
    Consultant Contract Process NTP Issued 10/07/2009
    Consultant Contract Process Workhours Approved 09/30/2009