Project Description:
BOSTON- CHELSEA- TOBIN BRIDGE TOLL PLAZA AND ADMINISTRATION BUILDING DEMOLITION
Demolish the existing Toll Plaza, including toll booths, toll islands and overhead canopy. The work also includes filling the void space of the toll booth with a pre-cast concrete slab, removing all the utilities that feed the plaza area, installing shielding on the upper deck to protect traffic on the lower deck, creating a work zone using temporary concrete barrier and installing temporary signage for construction
Location:
  • City of Boston
  • City of Chelsea
  • Resident Engineer: Michael Barry
    Construction Contract Value: $5,099,940.45
    Construction Bid Price: $3,650,383.00
    Initial Construction Estimate: $2,568,000.00
    District: District 6

    Contracts (2) Progress
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 85136 -- Construction Contract
    Tobin Bridge Administration Building and Various Structures Demolition . DCAMM Category: GENERAL BUILDING CONSTRUCTION Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/08/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Tobin
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/20/2009
    Project Initiation Form PIF Entered 11/20/2009
    Project Initiation Form PRC Submitted 11/20/2009
    Project Review Committee PRC Approved 05/13/2010
    Project Status Advertised 09/27/2014
    Project Management
    100% Design 100% Plans Complete 06/05/2015
    Final Design PS&E Received 06/02/2014
    Final Design PS&E to FAPRO 09/10/2014
    Final Design PS&E to FAPRO 06/05/2015