Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- CHELSEA- DECK REHABILITATION ON TOBIN BRIDGE, B-16-017, FROM C4 TO C30 (PHASE VII) INCLUDING STRUCTURAL STEEL REPAIRS TO CHELSEA CROSS-GIRDERS & RELATED WORK TO EVERETT STREET ON-RAMP, CLEANING AND PAINTING, DRY STANDPIPE INSTALLATION
This $41.6 million project involves repairing a section of the deck of the Tobin Bridge, which carries Route 1 traffic between the Charlestown neighborhood of Boston and Chelsea. The project will occur on a section of the bridge known as the “approach spans” in Chelsea, and will consist of resurfacing parts of Route 1 southbound (the upper deck) and the Everett Avenue ramp, and making structural repairs and resurfacing parts of Route 1 northbound (the lower deck) and the Beacon Street ramp. Construction operations are scheduled to begin by spring 2018 and work is currently expected to be completed by the end of 2020. During the spring, summer, and fall construction seasons of this project, one lane of Route 1 north will be closed at all times in this area to allow for construction operations. During this project, there will also be overnight lane closures on Route 1 south to allow for milling and paving work as needed.
Location:
  • City of Boston
  • City of Chelsea
  • Construction Begins: Autumn 2017
    Resident Engineer: Eric Feeley
    Construction Bid Price: $41,637,112.00
    District: District 6

    Contracts (2) Progress
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 98626 -- Construction Contract
    Structural Steel Repairs, Painting and Deck Repairs on the Maurice J. Tobin Memorial Bridge Br. Nos. (B-16-017=C-09-006) (Including Ramps) Route 1 over the Mystic River (Phase Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/19/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Tobin
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/20/2009
    Project Initiation Form PIF Entered 11/20/2009
    Project Initiation Form PRC Submitted 11/20/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Status Advertised 10/22/2016
    Project Management
    100% Design 100% Package Received 06/30/2016
    100% Design 100% Package Comments to DE 08/15/2016
    75% Design 75% Package Received 04/10/2017
    Final Design PS&E Received 10/06/2016
    Final Design PS&E to FAPRO 10/18/2016
    Final Design PS&E Received - Resub 1 06/08/2017