Project Description:
BOSTON- CHELSEA- STRUCTURAL CLEANING & PAINTING, STEEL & CONCRETE REPAIRS ON TOBIN BRIDGE, B-16-017
Undertake location-specific cleaning and painting of the Maurice J. Tobin bridge from C4 – C30 (lower section) and C4 - C36 (upper section), C4 - C30 (Everett Ave Ramp) and C4 - C-13 (Beacon Street Ramp). The purpose of this Contract is to clean, remove the existing paint system to bare metal from the superstructure of the bridge, repair steel and concrete on the Tobin Bridge as needed.
Location:
  • City of Boston
  • City of Chelsea
  • Construction Begins: Autumn 2023
    Resident Engineer: Jose Eusebio
    Construction Bid Price: $109,145,207.00
    District: District 6

    Contracts (2) Progress
    # 122602 -- Construction Contract
    Structural Cleaning & Painting, Steel & Concrete Repairs on Tobin Bridge, B-16-017=C-09-006
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/25/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: Tobin
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/20/2009
    Project Initiation Form PIF Entered 11/20/2009
    Project Initiation Form PRC Submitted 11/20/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 05/05/2021
    25% Design 25% Package Received 08/07/2020
    25% Design 25% Package Comments to DE 10/30/2020
    75% Design 75% Package Received 12/21/2020
    Final Design PS&E Received 12/06/2021
    Final Design PS&E to FAPRO 06/20/2023
    Final Design PS&E Received - Resub 1 06/05/2023