DISTRICT 4- SCHEDULED & EMERGENCY BRIDGE STRUCTURAL REPAIRS AT VARIOUS LOCATIONS
These contracts are required for maintenance and repairs of bridges and have to be active at all times to respond to bridge emergencies. The money in the existing contract has been more than 90% spent and the remaining money is already committed for ongoing repairs. This contract must be in place to respond to emergencies and continue with repairs and maintenance of MassDOT bridge assets.
Location:
Resident Engineer: Thomas Zizza
Construction Contract Value: $7,327,656.00
Construction Bid Price: $2,322,556.00
Initial Construction Estimate: $3,840,460.00
District: District 4

Contracts (1) Progress
# 77139 -- Construction Contract
Scheduled and Emergency Bridge Structural Repairs at Various Locations. Re-Advertised 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/13/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/24/2009
    Project Initiation Form PIF Entered 11/24/2009
    Project Initiation Form PRC Submitted 11/24/2009
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 02/26/2010
    Project Status Advertised 12/08/2012
    Project Status Advertised 04/06/2013
    Project Management
    Final Design PS&E Received 08/21/2012
    Final Design PS&E Received 03/27/2013
    Final Design PS&E Received 06/10/2013
    Final Design PS&E to FAPRO 10/30/2012
    Final Design PS&E to FAPRO 04/02/2013