Project Description:
SOUTHBRIDGE- BRIDGE RECONSTRUCTION, S-21-002, ROUTE 131 (MAIN STREET) OVER QUINEBAUG RIVER
Rehahabilitation of stone arch and related work (sidewalk, railing, etc.)
Location:
  • Town of Southbridge
  • Resident Engineer: Peter Kurt
    Construction Bid Price: $4,743,639.00
    District: District 3

    Contracts (5) Progress
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 89760 -- Construction Contract
    Bridge Rehabilitation Br. No. S-21-002 (Concrete Stone Arch) Main Street (Route 131) over the Quinebaug River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/17/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/09/2009
    Project Initiation Form PIF Entered 05/13/2011
    Project Initiation Form PRC Submitted 05/13/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 07/25/2015
    Project Management
    100% Design 100% Package Received 05/13/2014
    25% Design Design Public Hearing 06/19/2014
    75% Design 75% Package Received 10/03/2012
    Final Design PS&E Received 12/02/2014
    Final Design PS&E Received 03/17/2015
    Final Design PS&E Received 05/19/2015
    Final Design PS&E Received 06/30/2015
    Final Design PS&E to FAPRO 07/22/2015
    Consultant Contract Process NTP Issued 06/21/2011