Project Description:
WEBSTER- BRIDGE PRESERVATION, W-12-023, W-12-024, W-12-025 & W-12-026, ALONG I-395
The work for the bridges mentioned above shall consist of deck work, joint work; full cleaning and painting structural steel; reconstructing the bridge approach wearing surface for a few; reconstruct the approach sidewalk to one bridge; guardrail work, slope paving; patching deterioration in concrete surfaces of the abutments, piers and walls. The reinforced concrete use for the superstructure joint work, the sections of the deck partially needed to be replaced, shall be high performance reinforced concrete. The deck on most of these bridges is not in need of wearing surface. Bridges with the drainage pipe or the weep holes system thru the deck require extension of the pipes below the structural steel members. Full painting of the structural steel will be required for these bridges. All the structural steel will be designated for cleaning and painting. All the steel shall be cleaned and painted in accordance with the latest MassHighway Supplemental Specification Section 961”Maintance painting of steel bridges”. Substructure elements shall be repaired as required. Concrete deterioration and hollow sections shall be excavated and surfaces shall be patched as required. Missing slope paving will be replaced and cleaned as it is needed.
Location:
  • Town of Webster
  • Resident Engineer: Kit Leong
    Construction Contract Value: $3,646,360.00
    Construction Bid Price: $2,997,360.00
    Initial Construction Estimate: $3,959,987.50
    District: District 3

    Contracts (2) Progress
    # 55042 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 67022 -- Construction Contract
    Rehabilitation of 7 Bridges (Including Painting) (W-12-023, W-12-024, W-12-025 and W-12-026) along Interrstate 395. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/25/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/11/2009
    Project Initiation Form PIF Entered 12/11/2009
    Project Initiation Form PRC Submitted 12/11/2009
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/02/2010
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 05/12/2010
    Final Design PS&E Received 08/31/2010