Project Description:
WHATELY- REHABILITATION OF HAYDENVILLE ROAD, FROM CONWAY ROAD TO THE WILLIAMSBURG T.L. (1.7 MILES)
Work for the Haydenville Road rehabilitation project in Whately will consist of reclaiming the existing paved surface, box widening with an HMA binder course and paving with an HMA modified top surface course . Work will include a new drainage system to improve storm water quality near the Northampton Reservoir, new pavement markings and guardrail repair and replacement. The project limits are as follows: Haydenville Rd from Conway Rd to the Williamsburg T.L., - drainage improvements may continue another 1,000 feet to an appropriate outlet for a total project length of 1.7 miles.
Location:
  • Town of Whately
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $11,939,625.30
    Estimated Total Federal Participating Construction Cost: $12,627,746.95
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: 100% Package Comments to DE (as of 02/28/2024 )

    Contracts (2) Progress
    # 115772 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77869 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: WHATELY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2026 and FFY 2027; Regional + Statewide STBG. MPO Project TEC Score 41/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,567,551.20
    State Cost: $1,391,887.80
    Total Cost: $6,959,439.00

    Planned Federal FY: 2026
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: WHATELY
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2026 and FFY 2027; Regional + Statewide STBG. MPO Project TEC Score 41/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $302,262.40
    State Cost: $75,565.60
    Total Cost: $377,828.00

    Planned Federal FY: 2027
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: WHATELY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2026 and FFY 2027; Regional + Statewide STBG. MPO Project TEC Score 41/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,138,744.00
    State Cost: $534,686.00
    Total Cost: $2,673,430.00

    Planned Federal FY: 2027
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: WHATELY
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2026 and FFY 2027; Regional + Statewide STBG. MPO Project TEC Score 41/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $152,531.20
    State Cost: $38,132.80
    Total Cost: $190,664.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/15/2009
    Project Initiation Form PIF Entered 12/15/2009
    Project Initiation Form PRC Submitted 01/20/2010
    Project Review Committee PRC Approved 11/17/2011
    Project Management
    100% Design 100% Package Received 11/21/2023
    100% Design 100% Package Comments to DE 02/28/2024
    25% Design 25% Package Received 02/21/2019
    25% Design 25% Package Received - Resub 1 04/02/2021
    25% Design Design Public Hearing 01/12/2022
    75% Design 75% Package Received 05/06/2023
    75% Design 75% Package Comments to DE 08/08/2023