Project Description:
LUDLOW- PALMER- STURBRIDGE- RESURFACING & RELATED WORK AT INTERCHANGES 7, 8 & 9 ON I-90
Work consists of resurfacing, repairing the pavement and sign upgrades on I-90 at interchanges 7, 8 and 9. Interchange 7 is in Ludlow at MM 54.8. The ramp system and toll plaza area right up to Rte. 21 will be resurfaced. Interchange 8 is in Palmer at MM 62.6. The ramp system and toll plaza area right up to Rte. 32 will be resurfaced. Interchange 9 is in Sturbridge at MM 78.3. The sign work is the reconstruction of a sign bridge base near the interchange itself.
Location:
  • Town of Ludlow
  • Town of Palmer
  • Town of Sturbridge
  • Project Manager: John Gendall
    Estimated Total Contract Cost: $1,696,695.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project