CHARLTON- BRIDGE DECK REPLACEMENT, C-06-041, HAMMOND HILL OVER I-90
CHARLTON- BRIDGE DECK REPLACEMENT, C-06-041, HAMMOND HILL OVER I-90
Location:
  • Town of Charlton
  • Resident Engineer: Kevin Troy
    Construction Contract Value: $2,162,071.00
    Construction Bid Price: $1,965,519.00
    Initial Construction Estimate: $1,936,484.00
    District: District 3

    Contracts (1) Progress
    # 60230 -- Construction Contract
    Bridge Deck Replacement (C-06-041) - Hammond Hill Road over I-90. (MTA) (092-573) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/30/2009
    Contract Information
    Project Designer:
    Funding Source: Undetermined
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/16/2009
    Project Initiation Form PIF Entered 12/17/2009
    Project Initiation Form PRC Submitted 12/17/2009
    Project Review Committee PRC Approved 05/16/2009
    Project Status Advertised 05/16/2009