Project Description: |
KINGSTON- DUXBURY- INTERSECTION IMPROVEMENTS AT ROUTE 3 RAMPS (NB/SB) AND ROUTE 3A (TREMONT STREET)
This project includes roadway widening to accommodate 5 to 8-foot shoulders, new sidewalk on the north side of Tremont Street extending from the Tremont Place driveway to the Tremont Street/Route 3 Northbound Ramps intersection and on the south side of Tremont Street from the Tremont Street/Route 3 Northbound Ramps intersection to Baypath Road, new traffic control signals at the Tremont Street/Route 3 Northbound and Southbound Ramp intersections, pavement markings and signing, and pavement milling and paving.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2027 |
Project Manager: | Joseph Gyujong Yoo |
Estimated Total Contract Cost: | $2,835,000.00 |
Estimated Total Federal Participating Construction Cost: | $3,051,887.50 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|