GREENFIELD- RESURFACING & RELATED WORK ON ROUTE 2, FROM INTERSTATE 91 TO WEST OF THE GREENFIELD GILL T.L. (2.6 MILES)
Work for the Route 2 resurfacing project in Greenfield will consist of milling the existing paved surface and resurfacing with hot mix asphalt pavement course modified top. Work will also include repairing hot mix asphalt berm, repairing guardrail as needed, and new pavement markings. The project limits are as follows: Route 2 from Interstate 91 to the Gill town line at the Falls River (MM 49.93 to MM 52.79), for a project length of 2.86 miles.
Location:
  • Town of Greenfield
  • Resident Engineer: Garrett Postema
    Construction Contract Value: $4,056,013.00
    Construction Bid Price: $3,397,751.10
    Initial Construction Estimate: $2,907,953.00
    District: District 2

    Contracts (1) Progress
    # 80144 -- Construction Contract
    Roadway Resurfacing and Related Work along a Section of Route 2. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/20/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/29/2009
    Project Initiation Form PIF Entered 12/29/2009
    Project Initiation Form PRC Submitted 01/13/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 10/05/2013
    Project Management
    100% Design 100% Package Received 03/08/2013
    25% Design 25% Package Received 12/14/2012
    75% Design 75% Package Received 12/14/2012
    Final Design PS&E Received 08/28/2013
    Final Design PS&E to FAPRO 08/28/2013