Project Description:
CARVER: FAP# STP-002S(743)X ROADWAY RECONSTRUCTION AND RELATED WORK (INCLUDING SIGNALS) ALONG A SECTION OF ROUTE 58 (MAIN STREET) (606007)
This project involves the resurfacing of Route 58 (Main Street) from South Meadow Road to Purchase Street and related work. Related work includes realigning the intersection of 58/West Street/Meadowbrook Way to a 4-way intersection. Also, a pedestrian signal is proposed to be moved from its existing location on 58 between Center Street and West Street to the Route 58/West Street intersection. Other proposed work includes rehabilitation of drainage structures, new sidewalk extensions and replacement of guardrail, signage and pavement markings.
Location:
  • Town of Carver
  • Resident Engineer: Daniel Mastrangelo
    Construction Contract Value: $5,442,523.07
    Construction Bid Price: $4,783,825.50
    Initial Construction Estimate: $4,174,000.00
    District: District 5

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84996 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 58 (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/10/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/29/2009
    Project Initiation Form PIF Entered 02/17/2010
    Project Initiation Form PRC Submitted 03/02/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 07/28/2010
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 05/29/2014
    100% Design 100% Package Comments to DE 07/29/2014
    25% Design 25% Package Received 08/19/2011
    25% Design 25% Package Comments to DE 07/27/2012
    25% Design Design Public Hearing 11/26/2012
    75% Design 75% Package Received 11/14/2013
    75% Design 75% Package Comments to DE 02/11/2014
    Final Design PS&E Received 08/26/2014
    Final Design PS&E to FAPRO 09/03/2014