Project Description:
BERNARDSTON- RESURFACING & RELATED WORK ON ROUTE 10, FROM I-91 TO ROUTE 142
Work for the Route 10 resurfacing project in Bernardston will consist of milling the existing paved surface and resurfacing with hot mix asphalt pavement course modified top. Work will also include replacing signs and guardrail as needed, repairing hot mix asphalt berm, and new pavement markings. The project limits are as follows: Route 10 from the Interstate 91 southboud on-ramp to Mount Hermon Station Road (Route 142), MM 53.00 to MM 55.57, for a project length of 2.57 miles.
Location:
  • Town of Bernardston
  • Resident Engineer: John Burek
    Construction Contract Value: $1,817,891.38
    Construction Bid Price: $1,540,948.70
    Initial Construction Estimate: $1,548,049.00
    District: District 2

    Contracts (1) Progress
    # 75949 -- Construction Contract
    Resurfacing and Related Work (Including 2 Bridge Deck Repairs) on a Section of Route 10 (Northfield Road) . Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/01/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/29/2009
    Project Initiation Form PIF Entered 12/29/2009
    Project Initiation Form PRC Submitted 01/13/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/08/2010
    Project Status Advertised 10/13/2012
    Project Management
    75% Design 75% Package Received 02/16/2010
    75% Design 75% Package Comments to DE 12/03/2010
    Final Design PS&E Received 06/23/2011
    Final Design PS&E Received 08/11/2011
    Final Design PS&E Received 03/01/2012
    Final Design PS&E Received 09/12/2012
    Final Design PS&E to FAPRO 09/13/2012