DEERFIELD- WHATELY- RESURFACING & RELATED WORK ON ROUTES 5 &10, FROM OLD STATE ROAD TO CONWAY ROAD (1.1 MILES)
Work for the Routes 5 and 10 Resurfacing project in Whately and Deerfield will consist of milling the existing paved surface and resurfacing with hot mix asphalt pavement course modified top. Work will also include new sidewalks, crosswalks and ped signals at Elm Street, replacing signs and guardrail as needed, repairing hot mix asphalt berm, and new pavement markings. The project limits are as follows: Route 5&10 from 500' south of Old State Road in Whately to North Hillside Road in Deerfield, MM 33.21 to MM 36.71, for a project length of 3.50 miles.
Location:
  • Town of Deerfield
  • Town of Whately
  • Construction Begins: Summer 2020
    Resident Engineer: Jay Niedbala
    Construction Bid Price: $3,632,766.75
    District: District 2

    Contracts (2) Progress
    # 111310 -- Construction Contract
    Resurfacing and Related Work (Including Signals) along Section of Greenfield and State Roads (Route 5) Completed
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/13/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/29/2009
    Project Initiation Form PIF Entered 12/29/2009
    Project Initiation Form PRC Submitted 01/13/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 07/29/2019
    100% Design 100% Package Comments to DE 10/09/2019
    100% Design 100% Plans Approved 12/04/2019
    100% Design 100% Plans Complete 12/04/2019
    25% Design 25% Package Received 11/01/2017
    25% Design 25% Package Comments to DE 07/30/2018
    25% Design 25% Package Approved 09/03/2018
    25% Design Design Public Hearing 11/13/2018
    25% Design 25% Plans Complete 09/03/2018
    75% Design 75% Package Received 04/19/2019
    75% Design 75% Package Comments to DE 05/27/2019
    Final Design PS&E Received 01/08/2020
    Final Design PS&E to FAPRO 03/09/2020