CHELMSFORD- LOWELL- GUIDE & TRAFFIC SIGN REPLACEMENT ON THE LOWELL CONNECTOR
This project will provide for the replacement and updating of all guide and traffic signs along the Lowell Connector from the I-495/US 3 interchange (Exits 1 and 2) northerly to and including the Gorham Street interchange (Exit 5C), including applicable signs on intersecting streets.
Location:
  • Town of Chelmsford
  • City of Lowell
  • Resident Engineer: Paul Pascucci
    Construction Contract Value: $1,307,155.00
    Construction Bid Price: $1,077,777.77
    Initial Construction Estimate: $1,207,375.00
    District: District 4

    Contracts (1) Progress
    # 79869 -- Construction Contract
    Fabrication and Installation of Overhead and Ground Mounted Guide Signs along the Lowell Connector. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/30/2009
    Project Initiation Form PIF Entered 12/30/2009
    Project Initiation Form PRC Submitted 12/30/2009
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 03/01/2010
    Project Status Advertised 09/21/2013
    Project Management
    100% Design 100% Package Received 02/11/2013
    25% Design 25% Package Received 06/14/2010
    25% Design 25% Package Comments to DE 07/01/2010
    25% Design 25% Package Approved 07/01/2010
    75% Design 75% Package Received 09/13/2010
    Final Design PS&E Received 08/23/2013
    Final Design PS&E to FAPRO 09/09/2013
    Consultant Contract Process Scope to DE 01/05/2010
    Consultant Contract Process NTP Issued 01/27/2010
    Consultant Contract Process Workhours Approved 01/26/2010