Project Description:
TAUNTON- RECONSTRUCTION OF ROUTE 44 (DEAN STREET), FROM ARLINGTON STREET TO ROUTE 104 (SOUTH MAIN STREET)
Work on this project consists of roadway improvements along Route 44 (Dean Street) just east of Arlington Street and continue easterly to just west of the intersection with Route 104. Also included will be intersection improvements and the replacement of the existing traffic signals at Longmeadow Road / Gordon Owen Parkway,reconstruction of sidewalks, and drainage improvements.
Location:
  • City of Taunton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2022/2023
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $19,383,740.28
    Estimated Total Federal Participating Construction Cost: $21,955,827.90
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 09/10/2022 )

    Contracts (3) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/07/2010
    Project Initiation Form PIF Entered 01/07/2010
    Project Initiation Form PRC Submitted 01/12/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/08/2010
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 01/19/2022
    100% Design 100% Package Comments to DE 02/28/2022
    25% Design 25% Package Received 08/29/2018
    25% Design 25% Package Comments to DE 01/18/2019
    25% Design Design Public Hearing 02/12/2020
    75% Design 75% Package Received 11/11/2020
    75% Design 75% Package Comments to DE 02/08/2021
    Final Design PS&E Received 07/11/2022
    Final Design PS&E to Peer Reviewer 08/09/2022
    Final Design Peer Review Comments to DE 08/24/2022
    Final Design PS&E Received - Resub 1 08/26/2022