Project Description:
LANESBOROUGH- BRIDGE REPLACEMENT, L-03-009, MINER ROAD OVER TOWN BROOK
In general, the work to be done under this contract involves the replacement of the Bridge No. L-03-009, including installation of temporary control of water, the complete demolition of the existing superstructure, partial demolition of the existing substructure, the construction of new cast-in-place abutments, footings, and wingwalls, installation of driven steel H-piles, and the installation of precast concrete deck beams. The work includes, but is not limited to, the following: 1. Removal and disposal of the existing structure to the limits shown on the construction plans. 2. Installation of an approved water control system for the duration of the entire substructure and retaining wall construction, excavation, and the placement of riprap below the waterline. 3. Construction of a new steel pile supported abutment, precast concrete deck beams, reinforced concrete deck slab and safety curbs, S3-TL4 bridge railing, reinforced concrete highway guardrail transitions, wingwalls and footings as shown on the construction plans. 4. Installation of a new 8” diameter insulated water line, including fittings, bridge and wall mountings and connection to the existing water main. Installation of a temporary 1” diameter service line and connection to the existing water main. Installation of a temporary support structure for the temporary line, spanning the Town Brook. 5. Construction of new concrete low retaining walls along both sides of the bridge approaches. 6. Roadway safety upgrades including wall-mounted bridge railing and approach guardrail. Full depth roadway construction between Sta. 0+08 and Sta. 6+21.
Location:
  • Town of Lanesborough
  • Resident Engineer: Erin Cooper
    Construction Contract Value: $1,638,502.00
    Construction Bid Price: $1,472,384.25
    Initial Construction Estimate: $1,779,047.00
    District: District 1

    Contracts (4) Progress
    # 54831 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70938 -- Construction Contract
    Bridge Replacement Br. No. L-03-009 (Concrete) Miner Road over the Town Brook. Completed
    # 73478 -- Design -- Bridge Open End
    Work will consist of inspection of MassDOT owned Dams and Spillway structures and the design of repairs and/or rehabilitation of the dams and spillway structures. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/17/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/15/2010
    Project Initiation Form PIF Entered 01/15/2010
    Project Initiation Form PRC Submitted 01/15/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/02/2010
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 05/31/2011
    25% Design 25% Package Received 06/04/2010
    25% Design 25% Package Comments to DE 08/25/2010
    25% Design 25% Package Comments to DE 10/27/2010
    25% Design Design Public Hearing 12/06/2010
    75% Design 75% Package Received 05/31/2011
    Final Design PS&E Received 08/26/2011
    Final Design PS&E to FAPRO 08/29/2011
    Consultant Contract Process Scope to DE 10/22/2009
    Consultant Contract Process NTP Issued 01/04/2010