| Project Description: |
DOUGLAS- NORTHBRIDGE- SUTTON- UXBRIDGE- RESURFACING & RELATED WORK ON ROUTE 146 (NB)
Route 146 Northbound will be resurfaced from a pavement joint, located just north of Mill Street in Uxbridge, northerly to a pavement joint, located just south of Boston Road in Sutton. The total project length is approximately 10 miles.
|
| Location: |
|
| Resident Engineer: | Peter Kurt![]() |
| Construction Contract Value: | $8,583,110.00 |
| Construction Bid Price: | $7,348,000.00 |
| Initial Construction Estimate: | $7,993,429.00 |
| District: | District 3 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||