Project Description: |
DOUGLAS- NORTHBRIDGE- SUTTON- UXBRIDGE- RESURFACING & RELATED WORK ON ROUTE 146 (NB)
Route 146 Northbound will be resurfaced from a pavement joint, located just north of Mill Street in Uxbridge, northerly to a pavement joint, located just south of Boston Road in Sutton. The total project length is approximately 10 miles.
|
Location: |
|
Resident Engineer: | Peter Kurt |
Construction Contract Value: | $8,583,110.00 |
Construction Bid Price: | $7,348,000.00 |
Initial Construction Estimate: | $7,993,429.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|