Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROCKTON- SIGNAL & INTERSECTION IMPROVEMENTS @ ROUTE 123 (BELMONT STREET)/LINWOOD STREET/LORRAINE AVENUE
Work on this project includes improvements for safety, congestion and mobility for all users along the corridor. This is the second of three projects proposed on Route 123. Work includes traffic signal installation and safety improvements at Route 123 (Belmont Street) /Linwood Street/Lorraine Avenue, roadway reconstruction, and related work is proposed. Related work includes construction of a bus turn in lane at the intersection of Route 123 and Angus Beaton Drive (entrance to Brockton High School). Also, reconstruction of sidewalks both sides of Belmont Street is proposed. In addition, new crosswalks, widening of Belmont Street shoulders and improved intersection geometrics are proposed.
Location:
  • City of Brockton
  • Construction Begins: Spring 2017
    Resident Engineer: Christopher Sera
    Construction Bid Price: $3,468,003.60
    District: District 5

    Contracts (5) Progress
    # 57823 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassHighway on an open end basis for various high crash locations in Old Colony Region. Final
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final
    # 97934 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals & ADA Improvements) along a Section of Route 123 (Belmont Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/20/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/21/2010
    Project Initiation Form PIF Entered 01/22/2010
    Project Initiation Form PRC Submitted 01/22/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/08/2010
    Project Status Advertised 09/24/2016
    Project Management
    100% Design 100% Package Received 08/11/2015
    100% Design 100% Package Comments to DE 12/30/2015
    25% Design 25% Package Received 06/21/2010
    25% Design 25% Package Comments to DE 03/12/2012
    25% Design Design Public Hearing 09/05/2012
    75% Design 75% Package Received 10/29/2013
    75% Design 75% Package Comments to DE 12/17/2014
    Final Design PS&E Received 05/11/2016
    Final Design PS&E to Peer Reviewer 06/06/2016
    Final Design Peer Review Comments to DE 06/23/2016
    Final Design PS&E Received - Resub 1 08/23/2016
    Consultant Contract Process Scope to DE 01/28/2010
    Consultant Contract Process NTP Issued 02/26/2010
    Consultant Contract Process Workhours Approved 02/18/2010