Project Description:
BOYLSTON- CLINTON- DRAINAGE IMPROVEMENTS ON ROUTE 70
The proposed project will eliminate five existing stormwater drainage discharges that direct runoff and accidental release materials to the Wachusett Reservoir. The work will include modification to the existing drainage system, installation of new structures and piping, construction of associated Best Management Practices, minor roadway improvements to address a sight distance issue, and related resurfacing.
Location:
  • Town of Boylston
  • Town of Clinton
  • Resident Engineer: Steven Miller
    Construction Contract Value: $2,213,814.00
    Construction Bid Price: $1,888,717.50
    Initial Construction Estimate: $2,341,770.00
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70089 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Drainage) on a Section of Route 70 (Boylston and Main Streets). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/09/2011
    Contract Information
    Project Designer: Other
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/22/2010
    Project Initiation Form PIF Entered 01/22/2010
    Project Initiation Form PRC Submitted 02/03/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 07/23/2011
    Project Management
    100% Design 100% Package Received 05/11/2011
    100% Design 100% Package Comments to DE 06/29/2011
    25% Design 25% Package Received 11/22/2010
    25% Design 25% Package Comments to DE 01/21/2011
    25% Design Design Public Hearing 03/15/2011
    Final Design PS&E Received 07/18/2011
    Final Design PS&E to FAPRO 07/20/2011
    Consultant Contract Process NTP Issued 09/03/2010