Project Description:
DUNSTABLE- RETAINING WALL CONSTRUCTION ON ROUTE 113
The project is designed to maintain the existing horizontal curve (R=360’+/-) layout. A minimum 340 foot radius is recommended for 35 MPH speed. The existing dry stone retaining wall is not supporting the roadway very well and is in need of repair/replacement. The Town has discussed the project and the need to acquire additional right-of-way with owners of the abutting property (Map 17 Lot 137), George & Susan McGovern. The proposed roadway layout is based on the existing travel way center line. The layout proposes a 244’+/- long horizontal curve with a radius of 360’ in front of Lot 137 connecting to the existing pavement centerline. The roadway will be reconstructed and the proposed pavement width is 25’ with two 11’ wide travel lanes marked by pavement markings with 1.5’ shoulders. The existing Steel Highway Guardrail Type SS will be replaced with a consistent appearance of a steel guardrail (weathering steel) system. The 2-foot offset from the edge of pavement to the face of guardrail will be grass. A reinforced concrete retaining wall, along with stone fascia, is proposed 3’ behind the guardrail posts. A double solid yellow no passing zone marking and solid white edge lines are proposed for the roadway.
Location:
  • Town of Dunstable
  • Resident Engineer: Arvind Patel
    Construction Contract Value: $779,712.00
    Construction Bid Price: $634,738.47
    Initial Construction Estimate: $645,806.20
    District: District 3

    Contracts (1) Progress
    # 73895 -- Construction Contract
    Retaining Wall Replacement and Related Work on a Section of Route 113. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/25/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/22/2010
    Project Initiation Form PIF Entered 01/22/2010
    Project Initiation Form PRC Submitted 02/03/2010
    Project Review Committee PRC Tabled 05/13/2010
    Project Review Committee Letter 10/07/2010
    Project Status Advertised 06/09/2012
    Project Management
    100% Design 100% Package Received 03/16/2012
    100% Design 100% Package Comments to DE 04/26/2012
    25% Design 25% Package Received 03/31/2011
    25% Design 25% Package Comments to DE 07/06/2011
    25% Design Design Public Hearing 06/09/2011
    75% Design 75% Package Received 11/03/2011
    75% Design 75% Package Comments to DE 12/16/2011
    Final Design PS&E Received 05/30/2012
    Final Design PS&E to FAPRO 06/06/2012
    Consultant Contract Process NTP Issued 10/07/2010