HOPKINTON- SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 135
The project involves intersection improvements at Route 85, Pleasant Street and Wood Street. The improvements include signal equipment upgrade, geometric modifications, and additional lanes at Route 85, possible signalization at Pleasant Street, and minor widening, geometric modifications and equipment upgrades at Wood Street. The project includes pavement rehabilitation from Ash Street to Wood Street, drainage improvements as needed, reconstructed sidewalks and wheelchair ramps, and streetscape enhancements in the town center.
Location:
  • Town of Hopkinton
  • Construction Begins: Autumn 2020
    Resident Engineer: Anthony Tavalone
    Construction Bid Price: $12,348,690.50
    District: District 3

    Contracts (1) Progress
    # 111720 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Sections of Routes 85 and 135 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/06/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/22/2010
    Project Initiation Form PIF Entered 01/22/2010
    Project Initiation Form PRC Submitted 02/03/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 06/27/2020
    Project Management
    100% Design 100% Package Received 02/03/2020
    100% Design 100% Package Comments to DE 03/06/2020
    25% Design 25% Package Received 01/27/2015
    25% Design 25% Package Received - Resub 2 06/16/2017
    25% Design Design Public Hearing 01/09/2018
    75% Design 75% Package Received 03/18/2019
    75% Design 75% Package Comments to DE 05/28/2019
    Final Design PS&E Received 06/09/2020
    Final Design PS&E to FAPRO 06/15/2020