Project Description:
HOLYOKE- SIGNAL & INTERSECTION IMPROVEMENTS AT HOMESTEAD AVENUE & LOWER WESTFIELD ROAD
The proposed project consists of widening both Lower Westfield Road and Homestead Avenue to add turning lanes and updating the traffic signals with new equipment. Shared accommodations for all users have been provided in accordance with applicable guidelines. The project will also include new sidewalks and wheelchair ramps, new curb and new striping and signage. The existing intersection is functionally deficient geometry and has an obsolete traffic signal system. The proposed improvements will be the first stage in a long range plan to improve traffic flow in the surrounding I-91 Exit 15 area.
Location:
  • City of Holyoke
  • Resident Engineer: Nicholas Corey
    Construction Contract Value: $1,701,694.00
    Construction Bid Price: $1,455,177.25
    Initial Construction Estimate: $1,537,529.25
    District: District 2

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79144 -- Construction Contract
    Intersection Reconstruction (Including Traffic Signals) at Lower Westfield Road, Homestead and Whitney Avenues. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/05/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/25/2010
    Project Initiation Form PIF Entered 01/25/2010
    Project Initiation Form PRC Submitted 01/26/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 08/10/2013
    Project Management
    100% Design 100% Package Received 04/29/2013
    100% Design 100% Package Comments to DE 05/28/2013
    25% Design 25% Package Received 09/02/2011
    25% Design 25% Package Comments to DE 11/17/2011
    25% Design Design Public Hearing 09/26/2012
    75% Design 75% Package Received 11/27/2012
    75% Design 75% Package Comments to DE 01/15/2013
    Final Design PS&E Received 07/08/2013
    Final Design PS&E to FAPRO 08/07/2013