DISTRICT 1- RESURFACING & RELATED WORK AT VARIOUS LOCATIONS ON I-90
This project proposes to mill and resurface 32 ± lane miles of Interstate I-90 in the towns of Lee, Becket, Otis, and Blandford; between Mile Markers 11 and 27. The milling and resurfacing includes the travel lanes and adjacent 1 foot of the outside shoulder. Also included in the project will be new pavement markings, reflectorized slotted pavement markers, and milled rumble strips as required. Safety improvements/ upgrades to guard rail end treatments and replacement of damaged panels will occur as required, along with all necessary traffic management.
Location:
  • Town of Becket
  • Town of Blandford
  • Town of Lee
  • Town of Otis
  • Resident Engineer: Christopher Dindio
    Construction Contract Value: $4,226,128.00
    Construction Bid Price: $3,657,763.80
    Initial Construction Estimate: $3,805,896.00
    District: District 1

    Contracts (2) Progress
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 72702 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 90. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/12/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/27/2010
    Project Initiation Form PIF Entered 01/27/2010
    Project Initiation Form PRC Submitted 02/02/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 02/04/2012
    Project Management
    25% Design 25% Package Received 12/23/2011
    75% Design 75% Package Received 12/23/2011
    75% Design 75% Package Comments to DE 01/11/2012
    Final Design PS&E Received 01/26/2012
    Final Design PS&E Received 01/31/2012
    Final Design PS&E to FAPRO 02/01/2012