Project Description:
NEWBURYPORT- MERRIMAC- CLEANING & PAINTING OF 3 BRIDGES ALONG I-95 & I-495
This project consists of cleaning & painting and minor structural repairs to 3 bridges along I-95 & I-495 in the towns of Merrimac & Newburyport.
Location:
  • Town of Merrimac
  • City of Newburyport
  • Resident Engineer: Joseph Breen
    Construction Contract Value: $2,752,366.00
    Construction Bid Price: $2,391,060.00
    Initial Construction Estimate: $3,420,289.00
    District: District 4

    Contracts (2) Progress
    # 60140 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final
    # 67217 -- Construction Contract
    Cleaning and Painting of 3 Bridges (N-11-018 & N-11-019 & M-16-006) along I-95 and I-495. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/08/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/27/2010
    Project Initiation Form PIF Entered 02/04/2010
    Project Initiation Form PRC Submitted 02/04/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 03/01/2010
    Project Status Advertised 09/04/2010
    Project Management
    Final Design PS&E Received 03/05/2010
    Final Design PS&E to FAPRO 08/30/2010