Project Description:
DISTRICT 3- DISTRICT 4- DISTRICT 5- WORK ZONE PORTABLE CAMERA SYSTEMS INSTALLATION (ITS)
This work consists of supplying a fully mobile Work Zone Intelligent Transportation Systems (ITS) trailers. The ITS trailers shall provide several subsystems including: CCTV camera, Variable Message Sign (VMS) and Radar Traffic Sensor System (RTSS) which will communicate wirelessly to the MassDOT Highway Operations Center (HOC). The Work Zone ITS refers to using technology to support more traditional work zone management and operational techniques.
Location:
Resident Engineer: Marie Natola
Construction Contract Value: $504,372.75
Construction Bid Price: $438,585.00
Initial Construction Estimate: $649,200.00

Contracts (1) Progress
# 69937 -- Construction Contract
Portable Video, Traffic Sensor and CMS Work Zone Equipment and Monitoring System (ITS). Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/06/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/02/2010
    Project Initiation Form PIF Entered 02/02/2010
    Project Initiation Form PRC Submitted 02/02/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Status Advertised 07/16/2011
    Project Management
    100% Design 100% Package Received 03/29/2011
    75% Design 75% Package Received 04/08/2010
    Final Design PS&E Received 07/11/2011
    Final Design PS&E to FAPRO 07/13/2011