Project Description:
BOURNE- MEDIAN INSTALLATION ON ROUTE 6 (SCENIC HIGHWAY)
Work on this project consists of installing a median and shoulders to the existing four travel lane cross section providing separation between the eastbound and westbound opposing directions.
Location:
  • Town of Bourne
  • Construction Begins: Summer 2025
    Resident Engineer: Nathan Jones
    Construction Bid Price: $30,015,931.60
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5

    Contracts (2) Progress
    # 129855 -- Construction Contract
    Median Installation on Route 6 (Scenic Highway)
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/04/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: BOURNE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC - $37,547,201; AC 2025-2028; CMAQ analysis to be completed (MassDOT note: project may include CMAQ-eligible work)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,200,000.00
    State Cost: $1,300,000.00
    Total Cost: $6,500,000.00

    Planned Federal FY: 2026
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: BOURNE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • STIP Action 5 - Decrease NHPP from $11m to $6.4m and added CMAQ via STIP Action 5. Original STIP. TFPC - $37,547,201; AC 2025-2028; CMAQ analysis to be completed (MassDOT note: project may include CMAQ-eligible work)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $3,683,333.60
    State Cost: $920,833.40
    Total Cost: $4,604,167.00
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,116,666.40
    State Cost: $1,279,166.60
    Total Cost: $6,395,833.00

    Planned Federal FY: 2027
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: BOURNE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC - $37,547,201; AC 2025-2028; CMAQ analysis to be completed (MassDOT note: project may include CMAQ-eligible work)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $8,437,760.80
    State Cost: $2,109,440.20
    Total Cost: $10,547,201.00

    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: BOURNE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC - $37,547,201; AC 2025-2028; CMAQ analysis to be completed (MassDOT note: project may include CMAQ-eligible work)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $7,600,000.00
    State Cost: $1,900,000.00
    Total Cost: $9,500,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/05/2010
    Project Initiation Form PIF Entered 02/05/2010
    Project Initiation Form PRC Submitted 02/08/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 04/05/2010
    Project Status Advertised 03/29/2025
    Project Management
    100% Design 100% Package Received 04/25/2024
    100% Design 100% Package Comments to DE 05/23/2024
    25% Design 25% Package Received 10/11/2022
    25% Design 25% Package Comments to DE 12/13/2022
    25% Design Design Public Hearing 06/08/2023
    75% Design 75% Package Received 01/16/2024
    Final Design PS&E Received 10/01/2024
    Final Design PS&E Received - Resub 1 12/31/2024
    Final Design PS&E Received - Resub 2 02/13/2025
    Final Design PS&E Received - Resub 3 03/04/2025