Project Description: |
FREETOWN- SUPERSTRUCTURE REPLACEMENT, F-09-010, N. MAIN STREET OVER ST 24
This project is to replace the superstructure on this bridge. This is necessary due to the "poor" condition of the concrete deck and sidewalk, and the "fair" condition of the steel beams and bearings.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2025 |
Project Manager: | Janhavi Limaye![]() |
Estimated Total Contract Cost: | $3,432,000.00 |
Estimated Total Federal Participating Construction Cost: | $3,744,000.00 |
Funding Provision: | This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 09/15/2022 ) |
|