Project Description: |
FREETOWN- BRIDGE REPLACEMENT, F-09-010, N. MAIN STREET OVER ST 24
The purpose of this project is to replace the bridge with a new one. The new bridge will consist of a 2-span continuous superstructure with a new substructure. The new substructure will include a new aesthetic pier. A full closure and detour will be required to construct the project.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2027 |
Project Manager: | Janhavi Limaye![]() |
Estimated Total Contract Cost: | $23,848,091.00 |
Estimated Total Federal Participating Construction Cost: | $25,028,549.00 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 09/15/2022 ) |
|
Bridges
|
|
|
|